Aylor Replacement Project Update - April 7, 2020

On April 7, 2020, School Superintendent David Sovine and Assistant Superintendent for Administration Al Orndorff informed the School Board that Branch Builds, the construction manager for the replacement Robert E. Aylor Middle School, and the Construction Management at Risk Team for the project have achieved a Guaranteed Maximum Price of $40,647,528 for construction of the school. The Guaranteed Maximum Price is based upon a 151,154 square foot structure as per RRMM Architects’ drawings dated December 10, 2019, and Addendums Number 1-9 as per Branch Builds’ Guaranteed Maximum Price which includes value engineering items. Dr. Sovine noted that the Guaranteed Maximum Price is $52,511 under the proposal’s fixed Guaranteed Maximum Price with the above-mentioned scope of work. Following the report on the Guaranteed Maximum Price for the project, the School Board adopted Branch Builds’ Guaranteed Maximum price of $40,647,528 for the construction of the replacement Robert E. Aylor Middle School, on a 7-0 vote.